01 · The hub

Springvale Energy Hub

Combining energy storage, solar, electric vehicle charging and emerging technology in one metropolitan hub.

It will provide:

  • 01Capacity and energy storage close to where it’s most needed
  • 02Network stability and support to the United Energy distribution network
  • 03Investment in longer duration energy storage
  • 04Renewable energy generation
  • 05Emerging technologies
02 · Location

Strategically located

Most metropolitan homes rely on energy carried over long distances from regional areas. The hub will store energy close to where it’s most needed, connected to the grid in close proximity to major load centres.

The site lies between Clarke and Westall Roads in Springvale South, within the City of Greater Dandenong.

03 · Recognition

Nationally recognised

In October 2024, Stage 1 received support under the Federal Government’s Capacity Investment Scheme (CIS), which underwrites investment and confirms the hub’s role in delivering renewable energy for Victoria and meeting Australia’s clean energy targets.

VICTORIA Melbourne 47 HA Entry Spring Road Westall Road Clarke Road Future PVsolarpanels Stage 2BESS PlannedStage 3BBESS Future EVchargingprecinct United Energyswitchingstation Stage 1BESS Stage 3ABESS
Current Planned Illustrative layout, not to scale
Project timeline

Planning approved, operations scheduled for 2028

We are here · Oct 2026
2015
  • All stagesFeasibility studies commence
2025
  • Stages 1, 2 and 3ADetailed design underway
  • Stage 1Grid connection approval
  • Stages 3B and 4Planning commences
2026We are here
  • Stage 3AGrid connection approval
  • Stages 1 and 2 · Aug 2026Planning permits received
  • Stage 2Grid connection approval
2027
  • Stages 1 and 2Pre-construction activities end
  • Stages 1 and 2Construction begins
  • Stage 3AConstruction begins
2028
  • Stages 1 and 2Operational
  • Stage 3AOperational
Complete Scheduled Stage 1 and 2 milestone
Battery energy storage

Stage 1

115MW
Power
262MWh
Energy
2hours
Duration

Stage 1 involves the construction and installation of a 115 megawatt (MW) / 262 megawatt hour (MWh) two-hour Battery Energy Storage System (BESS) at the project site.

The BESS will allow energy to be stored and released to the grid when it is most needed, helping to stabilise the grid when there are fluctuations in power supply.

Once operational, Stage 1 will supply the National Energy Market (NEM) with energy to power hundreds of thousands of homes each year.

An innovative story

From landfill to community asset

The Springvale Energy Hub solves the problem of how to transform an environmental liability into a community asset.

1970s
Sand quarry
to 2003
Landfill operation
2003+
Clay cap installed
2015–22
Cap reprofiled
Today
Energy hub in development
Cap works

The site operated as a sand extraction pit during the 1970s and landfill facility in the 1990s, before closing in 2003.

Progress Power has collaborated with specialists to repurpose the site and mitigate environmental risks. Victoria’s Environment Protection Authority (EPA) requires closed landfills to be capped to manage surface water flow and avoid leaching. Progress Power went beyond this, custom designing a cap to support a wide range of land use options.

The innovative cap involved installing a thick layer of clay rich soil between the top of the existing landfill cap and surface soil. The process was a success, eliminating almost all uncontrolled landfill gas emissions on the future Springvale Energy Hub site.

How the cap works
Surface soil Clay-rich soil layer New layer Existing landfill cap Landfill waste